Getting Your Site Ready for Ready Mix Concrete Delivery
Why site preparation matters before the mixer truck arrives
Ordering ready mix concrete is only half the job. The other half is making sure your site is set up so the mixer truck can discharge its load quickly and safely. A missed detail here can lead to a wasted pour, a damaged driveway, or a truck that cannot reach the pour area at all. This article walks through the key steps to take before the delivery day, so everything runs smoothly.
The aim is simple: you want concrete delivered when needed, poured without delay, and cured without problems. That depends on good planning and a few hours of groundwork. The steps below cover access, preparation of the discharge point, timing, and what to have on hand.
Check site access for the mixer truck
Mixer trucks are heavy and long. A typical truck needs a clear path at least 3.5 metres wide and a turning circle of about 20 metres. Low branches, narrow gates, parked cars, and soft ground can all stop the truck from reaching the pour area. Walk the route the truck will take and check for overhead cables, especially near the delivery point. If the truck has to reverse a long distance, arrange for someone to guide the driver.
Soft or steep ground is a common problem. If the access route crosses a lawn or a muddy patch, the truck can sink or lose grip. A temporary track of hardcore or heavy-duty ground protection mats can solve this. For very tight sites, a smaller mixer or a pump may be needed, but that is something to discuss with your supplier before the order is placed.
What to check at the access point
- Width and height clearance for the truck (including the chute at the back).
- Surface condition: firm, level, and able to take the weight of a loaded truck (around 26 to 30 tonnes).
- Turning space at the end of the route so the truck can leave without reversing far.
Prepare the discharge point
The driver will position the truck so the chute can reach the centre of your pour area. The standard chute is about 1.5 metres long, and extensions can add another metre or two. Beyond that, concrete has to be moved by wheelbarrow or pump. Plan the discharge point so the truck can get as close as possible to where the concrete is needed. If you rely on wheelbarrows, keep the distance short to avoid the concrete stiffening before it is placed.

Clear the area of debris, tools, and materials. If you are pouring a slab or a foundation, make sure the formwork is braced and level. For a driveway, the sub-base should be compacted and the edges set. Mark the pour area clearly, especially if the truck arrives early or in poor light. Have a plan for where the truck will park and how it will leave. A delivery that goes wrong often starts with a poorly thought-out discharge point.
Understand the delivery window
Ready mix concrete has a limited working life. From the moment the ingredients are mixed at the plant, the clock is ticking. Most suppliers aim for a delivery window of 30 to 60 minutes from the scheduled time. The concrete must be discharged within about two hours of batching, depending on the mix and the weather. Hot or windy conditions speed up the set, so the window shrinks.
You need concrete delivered when needed, not too early and not too late. Agree a specific arrival time with your supplier and have your team and tools ready before that time. If the truck arrives and you are still prepping, the concrete may start to set in the drum or in the wheelbarrow. That means a poor finish and a lot of extra work. A delay of even 15 minutes can cause problems on a hot day.
What to do while you wait
Use the time before the truck arrives to double-check everything. Wet the sub-grade lightly if the ground is dry, so it does not suck moisture out of the concrete. Have your tamping beam, floats, and edging tools clean and within reach. Make sure you have enough help. A typical pour needs at least two or three people: one to guide the chute, one to spread and level, and one to handle the wheelbarrow if needed.
Plan the pour sequence
A pour sequence is simply the order in which you fill the formwork. Start at the far end and work back towards the truck. That way you never have to walk over freshly placed concrete. If the pour is large, arrange for the truck to discharge in stages, or have a second truck timed to arrive as the first finishes. A gap in supply leads to cold joints, visible lines where old concrete meets new, and weakens the structure.
For a driveway or a path, pour in sections if the area is big. Use a screed board to level each section before moving on. For a slab, work in a consistent pattern, compacting and floating as you go. The key is to keep the concrete moving from the truck to its final position without stopping. That is where having concrete delivered when needed makes the difference between a smooth job and a rushed one.
Have the right equipment ready
Beyond the tools for placing and finishing, you need equipment for moving concrete if the chute cannot reach. A wheelbarrow is fine for small loads, but use a concrete barrow with a wide tyre and a shallow tray to avoid spillage. For larger volumes, a concrete pump or a conveyor belt may be better, though those need separate planning and cost.

Also have a source of water nearby for cleaning tools and the chute. Concrete left to dry on the truck's chute is hard to remove and can delay the next delivery. A bucket of water and a stiff brush should be enough. Keep the water away from the fresh pour, though, as excess water on the surface weakens the top layer.
Account for weather conditions
Weather affects how concrete behaves. In hot weather, concrete stiffens faster, so you need to work quickly and possibly add a retarder to the mix. In cold weather, the set slows down and the concrete may need protection from frost. If rain is forecast, cover the fresh pour with polythene sheeting as soon as it is finished. Rainwater on the surface can wash out the cement paste and leave a dusty, weak top.
Check the forecast a couple of days ahead and have a backup plan. If extreme heat or heavy rain is expected, consider rescheduling the delivery. Most suppliers will work with you to find a better time, as long as you give notice.
Communicate clearly with the supplier
By the time the truck is on its way, the supplier should know your site access details, the volume needed, and the mix specification. Confirm these details the day before. If anything changes on site, a blocked access, a broken tool, a late start, call the supplier straight away. They can often adjust the timing or the load size, but only if you tell them in time.
Good communication also helps with safety. Let the driver know about any hazards on site: overhead cables, soft ground, or tight corners. A driver who knows what to expect can position the truck more accurately and avoid accidents.
Final checks on the day
On the morning of the delivery, walk the site one last time. Check that the formwork is secure, the sub-grade is ready, and the access route is clear. Make sure the area where the truck will stand is firm and level. If you need to protect a driveway or a path from the truck's weight, lay down plywood or heavy mats. Have a plan for where the washout water will go after the chute is cleaned. Concrete washout is alkaline and can harm plants and waterways, so contain it in a designated area.
When the truck arrives, talk to the driver before they start to discharge. Confirm the mix, the volume, and the pour sequence. The driver can adjust the chute and the discharge rate to match your pace, but they need to know what you plan to do. A few minutes of conversation at the start can save an hour of trouble later.

Once the pour is underway, work steadily. Do not add extra water to the mix to make it flow better, that weakens the concrete and can cause cracking. If the concrete seems too stiff, ask the driver if they can add a plasticiser or a retarder. That is a better solution than watering it down.
After the pour is finished, cover and cure the concrete according to the mix specification. Curing means keeping the concrete moist and at a stable temperature for at least a few days. This step is often rushed, but it is what gives the concrete its final strength and durability.
Getting a site ready for ready mix concrete delivery is mostly about foresight. Check the access, prepare the discharge point, have the right tools and people, and communicate with the supplier. When those pieces are in place, the delivery itself becomes straightforward. And that is the whole point: a pour that goes to plan, with concrete that performs as expected, from the moment it leaves the truck to the day it finishes curing.